JKSSB JE Civil Estimating & Construction Management previous year questions with answers
Every Estimating & Construction Management question asked in the JKSSB JE Civil papers on this site, grouped by topic. Answers come from JKSSB's key; each has a short explanation (free here for a sample, all of them in the practice app).
Practise Estimating & Construction Management onlineEstimating & Costing
In long and short wall method of estimation, the length of long wall is the center to center distance between the wall and
- breadth of the wall
- half breadth of the wall on each side
- one forth breadth of the wall on each side
- one fifth breadth of the wall on each side
Show answer
Answer: (2) half breadth of the wall on each side
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
The Damp Proof Course (D.P.C) is measure in
- Cubic meter
- Square meter
- Meters
- Rupees per meter
Show answer
Answer: (2) Square meter
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
While submitting a tender the contractor is required to deposit some amount with the department, as guarantee of the tender, known as
- Bank guarantee
- Caution money
- Security deposit
- Earnest money
Show answer
Answer: (4) Earnest money
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Estimated value of a built up property at the end of its useful life without being dismantled is known as,
- Scrap value
- Salvage Value
- Market value
- Book value
Show answer
Answer: (2) Salvage Value
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Difference between cost of property and accumulated depreciation cost is known as
- Market value
- Salvage value
- Book value
- Capital value
Show answer
Answer: (3) Book value
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
The sinking fund is
- The fund for rebuilding a structure when its economic life is over.
- Raised to meet maintenance costs.
- The total sum to be paid to municipal authorities by the tenants.
- A part of the money kept in reverse for providing additional structures and structural modification.
Show answer
Answer: (1) The fund for rebuilding a structure when its economic life is over.
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Which of the following refers to the annual periodic payments made for the repayment of the capital invested?
- Annuity
- Sinking fund
- Depreciation
- Solatium
Show answer
Answer: (1) Annuity
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Filling work in trenches shall be carried out in layers of thickness not exceeding ______.
- 100mm
- 200mm
- 500mm
- 750mm
Show answer
Answer: (2) 200mm
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Construction Management
In a network diagram, an activity having a dotted arrow between two activity is referred as,
- Important activity
- Risky activity
- Dummy activity
- Delayed activity
Show answer
Answer: (3) Dummy activity
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
In the following network, choose the Critical Path from given options, (the number on the arrow shows duration of activity) The correct option is:
- A - B - C - D - E - F
- A - B - D - E - F
- A - B - C - E - F
- A - B - D - C - E - F
Show answer
Answer: (1) A - B - C - D - E - F
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
If the optimistic time (tₒ), most likely or probable time (tₘ), and pessimistic time (tₚ), for activity (A) are 2, 5 and 14 days respectively, then expected duration and variance of the activity are
- 2 and 5 days
- 6 and 4 days
- 14 and 7 days
- 16 and 5 days
Show answer
Answer: (2) 6 and 4 days
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
As per Critical Path Methodology (CPM) the earliest start time for an event (I) is 10 weeks. Activity (I-J) takes 4 weeks for completion. Event (J) starts after 20 weeks. Then the total float for activity (I-J) is,
- 2 weeks
- 6 weeks
- 12 weeks
- 16 weeks
Show answer
Answer: (2) 6 weeks
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
The difference between Late Start and Early Start Time of an activity is referred as,
- Float
- Progress of an activity
- Task of a work
- PERT task
Show answer
Answer: (1) Float
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
A scheduled activity may begin 10 days before the predecessor activity finishes. Then it's referred as an example of,
- Finish to start
- Finish to finish
- Start to finish
- Start to start
Show answer
Answer: (1) Finish to start
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Following is a Rate list for an earth excavation work:
S.No Item : earth work Rate Variable rate I Manual excavation Rs.10 /cum Nil II Machine excavation Rs. 4000 fixed Rs.2 /cum As per above rate list, estimated quantity of earth, for which the cost of excavation by machine will be equal to the cost of manual excavation, considering variable rate is
- 500 cum
- 1000 cum
- 2500 cum
- 3000 cum
Show answer
Answer: (1) 500 cum
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
The cost slop is defined as
- (Crash cost - Normal cost)/Normal time
- (Crash cost - Normal cost)/Crash time
- Crash cost/(Normal time-Crash time)
- (Crash cost-Normal cost)/(Normal time-Crash time)
Show answer
Answer: (4) (Crash cost-Normal cost)/(Normal time-Crash time)
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Which among the following, means statistical quality control of RCC work at civil construction site?
- Minimizing cost for removal of defective work
- Appling theory of probability to sample testing or inspection
- Minimizing in wastage of inspection cost
- Calculating risk probably to minimize utilization
Show answer
Answer: (2) Appling theory of probability to sample testing or inspection
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Consider the following pairs i. Net working — 1. actual performance of the task and consume time or resources, represented by an arrow ii. Activity — 2. an arrow diagram obtained by connecting all the activities of a project in a logical sequence iii. Event — 3. sequential relationship between other activities but does not consume resources, and represented by a circle iv. Dummy activity — 4. start or completion of tasks and does not consume time or resources, and represent precedence relationship between real activities. Which of the pair given below is correctly matched
- (i)-(2), (ii)-(1), (iii)-(3), (iv)-(4)
- (i)-(2), (ii)-(4), (iii)-(3), (iv)-(1)
- (i)-(3), (ii)-(1), (iii)-(4), (iv)-(2)
- (i)-(3), (ii)-(4), (iii)-(1), (iv)-(2)
Show answer
Answer: (1) (i)-(2), (ii)-(1), (iii)-(3), (iv)-(4)
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
With reference to the following network which statement is incorrect?
- Events 3 and 4 occur after event 2
- Event 7 can occur after event 4
- Event 7 preceded event 6
- Event 5 follows event 3
Show answer
Answer: (2) Event 7 can occur after event 4
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Statement 1: Security deposit is an amount of money which is nonrefundable, even after the maintenance period is over. Statement 2: Retention money always forfeited by the department even after the finalization of maintenance or adjustment of the claim is over. The correct combination is
- Both statement (1) and statement (2) are individually true and statement (1) is correct explanation of statement (2)
- Statement (1) is true but statement (2) is false
- Statement (1) is false but statement (2) is true
- Both the statement (1) and Statement (2) are individually false
Show answer
Answer: (4) Both the statement (1) and Statement (2) are individually false
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Match the list-1 with list-2 and select the correct answer using the codes given below, List -1 (Description) — List -2 (Purpose details or functions) a. Estimation — 1. Setting objectives and determining a course of action for achieving the project objectives. b. Planning — 2. The science of calculating the different load requirements, so that proposed structure can easily withstand worst-case scenarios for a particular duration. c. Quality control — 3. To ascertain the probable cost of a proposed project. d. Designing — 4. Testing units and determining whether the materials are within the specifications for the final product . Correct codes:
- a-1, b-2, c-4, d-3
- a-3, b-1, c-4, d-2
- a-4, b-2, c-3, d-1
- a-1, b-2, c-3, d-4
Show answer
Answer: (2) a-3, b-1, c-4, d-2
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
The expected time (E) of a PERT activity in terms of optimistic time (O), pessimistic time (P) and most likely time (M) is given by.
- E=(O+2M+P)/3
- E=(O+4M+P)/3
- E=(O+2M+P)/6
- E=(O+4M+P)/6
Show answer
Answer: (4) E=(O+4M+P)/6
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Match the list - I with List - II and select the correct answer using the codes given below the list. List - I — List - II a. Open tender — 1. The tender enquiry is sent only to one party. b. Limited tender — 2. Open for everyone and anyone can take part in the tendering process. c. Single tender — 3. Offer of tender is sent to limited parties and is not open for all.
- a-1, b-2, c-3
- a-2, b-3, c-1
- a-3, b-2, c-1
- a-3, b-1, c-2
Show answer
Answer: (2) a-2, b-3, c-1
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Which of the following statements is true? 1. CPM is activity - oriented network 2. PERT is activity oriented
- Only 1 is true
- Only 2 is true
- Both are false
- Both are true
Show answer
Answer: (1) Only 1 is true
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Which of the following earth moving machines has the shortest cycle time?
- Drag line.
- Hoe.
- Clam shell.
- Dipper shovel.
Show answer
Answer: (4) Dipper shovel.
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
The time estimates obtained from four contractors P, Q, R and S for executing a particular job are as under:
Contractor Optimistic time (tₒ) Most likely time (tₗ) Pessimistic time (tₚ) P 5 10 13 Q 6 9 12 R 5 10 14 S 4 10 13 Which one of the contractors is more certain about completing the work in time:
- Contractor P
- Contractor Q
- Contractor R
- Contractor S
Show answer
Answer: (2) Contractor Q
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Which of the following curves/line represents the total project cost versus time in the best way?
- Straight line
- S shaped curve
- U shaped curve
- Parabola
Show answer
Answer: (3) U shaped curve
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.