    As per Critical Path Methodology (CPM) the earliest start time for an event (I) is 10 weeks. Activity (I-J) takes 4 weeks for completion. Event (J) starts after 20 weeks. Then the total float for activity (I-J) is,

    1. 2 weeks
    2. 6 weeks
    3. 12 weeks
    4. 16 weeks
    Show answer

    Answer: (2) 6 weeks