JKSSB JE Civil 2025 · Question 113
Question 113 of the JKSSB Junior Engineer (Civil) OMR Exam 2025 (2 November) Question Paper (2 November 2025). Try it first, then open the answer. The explanation is in the practice app with the All-in-One Pass.
If the optimistic time (tₒ), most likely or probable time (tₘ), and pessimistic time (tₚ), for activity (A) are 2, 5 and 14 days respectively, then expected duration and variance of the activity are
- 2 and 5 days
- 6 and 4 days
- 14 and 7 days
- 16 and 5 days
Show answer
Answer: (2) 6 and 4 days