The expected time (E) of a PERT activity in terms of optimistic time (O), pessimistic time (P) and most likely time (M) is given by.
- E=(O+2M+P)/3
- E=(O+4M+P)/3
- E=(O+2M+P)/6
- E=(O+4M+P)/6
Show answer
Answer: (4) E=(O+4M+P)/6