JKSSB JE Civil 2025 · Question 117

Question 117 of the JKSSB Junior Engineer (Civil) OMR Exam 2025 (2 November) Question Paper (2 November 2025). Try it first, then open the answer. The explanation is in the practice app with the All-in-One Pass.

  1. JE Civil 2025 · 2 November · Q117 · Estimating & Construction Management · Construction Management

    Following is a Rate list for an earth excavation work:

    S.NoItem : earth workRateVariable rate
    IManual excavationRs.10 /cumNil
    IIMachine excavationRs. 4000 fixedRs.2 /cum

    As per above rate list, estimated quantity of earth, for which the cost of excavation by machine will be equal to the cost of manual excavation, considering variable rate is

    1. 500 cum
    2. 1000 cum
    3. 2500 cum
    4. 3000 cum
    Show answer

    Answer: (1) 500 cum