JKSSB JE Civil 2025 · Question 118

Question 118 of the JKSSB Junior Engineer (Civil) OMR Exam 2025 (2 November) Question Paper (2 November 2025). Try it first, then open the answer. The explanation is in the practice app with the All-in-One Pass.

  1. JE Civil 2025 · 2 November · Q118 · Estimating & Construction Management · Construction Management

    The cost slop is defined as

    1. (Crash cost - Normal cost)/Normal time
    2. (Crash cost - Normal cost)/Crash time
    3. Crash cost/(Normal time-Crash time)
    4. (Crash cost-Normal cost)/(Normal time-Crash time)
    Show answer

    Answer: (4) (Crash cost-Normal cost)/(Normal time-Crash time)