The time estimates obtained from four contractors P, Q, R and S for executing a particular job are as under:
Contractor Optimistic time (tₒ) Most likely time (tₗ) Pessimistic time (tₚ) P 5 10 13 Q 6 9 12 R 5 10 14 S 4 10 13 Which one of the contractors is more certain about completing the work in time:
- Contractor P
- Contractor Q
- Contractor R
- Contractor S
Show answer
Answer: (2) Contractor Q