JKSSB JE Civil 2023 · Question 107
Question 107 of the JKSSB Junior Engineer (Civil) OMR Exam 2023 (19 November) Question Paper (19 November 2023). Try it first, then open the answer. The explanation is in the practice app with the All-in-One Pass.
Which of the following curves/line represents the total project cost versus time in the best way?
- Straight line
- S shaped curve
- U shaped curve
- Parabola
Show answer
Answer: (3) U shaped curve