TGPSC HMWSSB Manager 2015 Paper 2 · Question 30

Question 30 of the TSPSC Manager (Engineering), HMWSSB, 2015: Paper 2 (Civil Engineering) (1 November 2015). Try it first, then open the answer and explanation.

  1. Manager 2015 Paper 2 (Civil) · Q30 · Building Materials & Construction · Construction & Estimation

    In earth work excavation, normally lead and lift is considered for preparation of road estimate

    1. 30 m and 1.5 m
    2. 20 m and 1.5 m
    3. 20 m and 2.0 m
    4. 30 m and 2.0 m
    Show answer

    Answer: (1) 30 m and 1.5 m

    The normal rate for earthwork in estimates includes an initial lead of 30 m (horizontal carriage) and a lift of 1.5 m (vertical raising). Extra lead or lift beyond these is paid for separately.