UPSC Civil Services (Main) 2026 · GS Paper III

UPSC Mains 2026 GS 3 · Q6: model answer

General Studies Paper III: Technology, Economic Development, Bio-diversity, Environment, Security and Disaster Management · Science and Technology.

Q610 marks150 words2026 · GS Paper III

Distinguish between a Fast Breeder Reactor (FBR) and a thermal nuclear reactor. In the context of first indigenously developed prototype FBR at Kalpakkam, explain the term ‘criticality’. What are its implications for clean energy future of our country?

Syllabus: Science and Technology · Energy and nuclear technology

Model answer · free

Fast Breeder ReactorCriticalityThree-stage nuclear programmeClean energy

Nuclear reactors are classed by the speed of the neutrons that keep fission going. Thermal reactors, such as India's PHWRs and the Kudankulam VVERs, slow neutrons down with a moderator. A Fast Breeder Reactor (FBR) uses fast neutrons and breeds more fissile fuel than it burns. The 500 MWe Prototype Fast Breeder Reactor (PFBR) at Kalpakkam, designed by IGCAR and built by BHAVINI with over 200 Indian firms, attained first criticality on 6 April 2026.

1. FBR vs thermal reactor

FeatureThermal reactor (e.g. PHWR)Fast Breeder Reactor (PFBR)
NeutronsSlowed-down (thermal) neutronsFast neutrons
ModeratorHeavy water, light water or graphiteNone
FuelNatural or low-enriched uraniumUranium–plutonium mixed oxide (MOX)
CoolantHeavy or light waterLiquid sodium
Fuel balanceBurns more fissile material than it makesBreeds more fissile material than it burns
Role in IndiaStage IStage II
Fast Breeder Reactor vs thermal reactor
  • Breeding: a blanket of uranium-238 around the core absorbs fast neutrons and turns into plutonium-239; later, a thorium blanket can make uranium-233.
  • Why sodium: liquid sodium carries heat well without slowing neutrons and works at near-atmospheric pressure, but it burns in air and reacts violently with water, so it needs special safety systems.
  • Fuel efficiency: thermal reactors use only a small part of uranium's energy, while FBRs with fuel recycling can extract many times more from the same uranium.

2. Criticality explained

  • Meaning: a reactor is critical when each fission causes, on average, exactly one more fission, so the chain reaction sustains itself at a steady rate. Below this it is subcritical and dies out; above it, it is supercritical and power rises.
  • First criticality: the first time a new reactor's chain reaction becomes self-sustaining, at very low power. It is a controlled, safe milestone, not an emergency.
  • Control: operators reach and hold criticality by slowly withdrawing neutron-absorbing control rods.
  • What follows: low-power physics tests, step-by-step power raising, grid connection and commercial operation.
Core loading of MOX fuel (from March 2024)
Control rods slowly withdrawn
First criticality: self-sustaining chain (6 April 2026)
Low-power physics tests
Power raising, grid connection, commercial operation
From fuel loading to power at Kalpakkam

3. Implications for India's clean energy future

  • Stage II of Bhabha's programme: the PFBR multiplies India's modest uranium by producing plutonium and, later, uranium-233 for stage III thorium reactors, using one of the world's largest thorium reserves.
  • Low-carbon baseload: nuclear power gives round-the-clock electricity to balance solar and wind; non-fossil sources are about 55% of capacity, but coal still produces about 70% of electricity.
  • Net zero and 100 GW: fast reactors support the goal of 100 GW of nuclear capacity by 2047 and net zero by 2070; two more 500 MWe FBRs are at the pre-project stage at Kalpakkam.
  • Closed fuel cycle: reprocessing and recycling reduce long-lived waste.
  • Technology leadership: India will be the second country after Russia with a commercial fast breeder; the SHANTI Act, 2025 now allows private Indian companies into nuclear power, though reprocessing stays with the Centre.

4. Concerns

  • Delays and cost: construction began in 2004, and criticality came over 15 years late.
  • Safety: sodium handling and plutonium security need strict regulation by an independent AERB.

The PFBR's criticality turns Bhabha's vision into reality. Timely commercial operation and fleet-mode FBRs can make nuclear power a pillar of clean energy security.

Every model answer here is free

The ₹149 All-in-One Pass opens the rest of the site for 12 months: UPSC Prelims GS Paper I and CSAT with explanations, practice quizzes and timed tests, UPSC CAPF and EPFO, the previous papers of every APPSC, TSPSC, police and SSC exam, every mock test series and the study books.

₹149 · valid for 12 months from the day you pay, on every exam · pay by UPI, card or net banking

Get it for ₹149