    In a centre-tap full wave rectifier, V_m is the peak voltage between the centre-tap and one of the secondary. The maximum voltage across the reverse biased diode is

    1. V_m
    2. 2 V_m
    3. V_m/2
    4. 3 V_m
    Show answer

    Answer: (2) 2 V_m

    Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.