Recirculation in activated sludge process is done to
- Dilute the incoming sewage
- Dampen the effect of the flow variation
- Operate the plant continuously
- Supply seed materials to the aeration tank
Show answer
Answer: (4) Supply seed materials to the aeration tank
Part of the settled sludge from the secondary clarifier is returned to the aeration tank so that the incoming sewage is seeded with an active population of acclimatised micro-organisms, keeping the MLSS at the required level.