TGPSC HMWSSB Manager 2015 Paper 2 · Question 27
Question 27 of the TSPSC Manager (Engineering), HMWSSB, 2015: Paper 2 (Civil Engineering) (1 November 2015). Try it first, then open the answer and explanation.
Cornice and coping is measured in ______
- Running meter & Square meter
- Running meter & Running meter
- Square meter & Square meter
- Square meter & Running meter
Show answer
Answer: (2) Running meter & Running meter
Cornices and copings are linear features of a building, so in estimates both are measured in running metres, with their cross-section described in the item. Area units are used for items such as plastering and flooring.