JKSSB JE Civil Surveying previous year questions with answers
Every Surveying question asked in the JKSSB JE Civil papers on this site, grouped by topic. Answers come from JKSSB's key; each has a short explanation (free here for a sample, all of them in the practice app).
Practise Surveying onlineSurveying
Which of the following set of terms does not relate to operation of a theodolite?
- Transiting and inverting
- Face left and face right
- Right swing and left swing
- Gauging and sounding
Show answer
Answer: (4) Gauging and sounding
Transiting (plunging) the telescope, face left/face right observations and swinging the telescope right or left are all theodolite operations. Gauging (measuring stream discharge) and sounding (measuring water depth) belong to hydrographic surveying, not to theodolite work.
If the whole circle bearing is 315°20′, its quadrantal bearing would be
- S 36°30′ W
- N 44°40′ W
- N 57°24′ W
- S 60°40′ W
Show answer
Answer: (2) N 44°40′ W
A WCB between 270° and 360° lies in the NW quadrant, so QB = N (360° − WCB) W = N (360° − 315°20′) W = N 44°40′ W.
Error due to inclination of line of collimation in levelling across a river can be eliminated by
- Reversion
- Reciprocal ranging
- Reciprocal levelling
- Keeping level in middle
Show answer
Answer: (3) Reciprocal levelling
Across a river the level cannot be set up midway between the two points, so reciprocal levelling is used: readings are taken with the level near each bank in turn and the mean of the two apparent differences of level cancels the collimation error (and curvature and refraction).
The length of a survey line when measured with a chain of 20 m nominal length was found to be 841.5m. If the chain used is 0.1 m too long, the correct length of the measured line is
- 845.7 m
- 837.3 m
- 841.6 m
- 839.4 m
Show answer
Answer: (1) 845.7 m
True length = (L′/L) × measured length = (20.1/20) × 841.5 = 845.7 m. A chain that is too long gives a measured length that is too short, so the correction is positive.
In any closed traverse, if the survey work is error free, then I. The algebraic sum of all the latitudes should be equal to zero II. The algebraic sum of all the departures should be equal to zero III. The sum of the northings should be equal to the sum of the southings Which of the above statements are correct?
- I and II
- I and III
- II and III
- I, II and III
Show answer
Answer: (4) I, II and III
For an error-free closed traverse the closing error is zero, so ΣL = 0 and ΣD = 0. ΣL = 0 simply means the sum of northings (+ latitudes) equals the sum of southings (− latitudes), so all three statements hold.
Consider the following statements: Reciprocal leveling eliminates the effect of I. Errors due to earth's curvature II. Errors due to atmospheric refraction III. Mistakes in taking levelling staff readings IV. Error due to line of collimation Which of these statements are correct?
- I, II and III
- I, III and IV
- II, III and IV
- I, II and IV
Show answer
Answer: (4) I, II and IV
In reciprocal levelling the true difference of level is the mean of the two apparent differences, so the errors of curvature, refraction (assumed equal in both observations) and collimation cancel out. Mistakes in reading the staff are blunders and are not eliminated by any method.
Consider the following statements about the characteristics of contours: I. Closed contour lines with higher values inside show a lake II. Contour is an imaginary line joining points of equal elevations III. Closely spaced contours indicate steep slope IV. Contour lines can cross each other in case an overhanging cliff Which of these statements are correct?
- II, III and IV
- I and II
- I and IV
- I, II and III
Show answer
Answer: (1) II, III and IV
Closed contours with higher values inside indicate a hill; a lake or depression has lower values inside, so I is wrong. A contour joins points of equal elevation, close spacing means a steep slope, and contours cross only at an overhanging cliff (or cave), so II, III and IV are correct.
Match List - I with List-II and select the correct answer using the codes given below the lists: List - I (Type of survey) — List - II (Purpose) i. Topographical survey — 1. To determine boundaries of fields, houses, etc. ii. Reconnaissance survey — 2. To find relics of antiquity iii. Cadastral survey — 3. To determine natural features of a country iv. Archaeological survey — 4. To determine possibility and rough cost of the surveying system to be adopted Choose the correct option:
- (i) - 3, (ii) - 4, (iii) - 1, (iv) - 2
- (i) - 3, (ii) - 1, (iii) - 4, (iv) - 2
- (i) - 2, (ii) - 4, (iii) - 1, (iv) - 3
- (i) - 2, (ii) - 1, (iii) - 4, (iv) - 3
Show answer
Answer: (1) (i) - 3, (ii) - 4, (iii) - 1, (iv) - 2
A topographical survey maps natural features (hills, rivers, forests); a reconnaissance survey is a preliminary look to judge feasibility and rough cost; a cadastral survey fixes property boundaries of fields and houses; an archaeological survey traces relics of antiquity. So i-3, ii-4, iii-1, iv-2.
Match List - I with List-II and select the correct answer using the codes given below the lists: List - I (Statement) — List - II (Situation) i. Accurate centering in plane table surveying is necessary for — 1. Inaccessible points ii. Exact orientation is more important than accurate centering for — 2. Open country with good intervisibility iii. The intersection method of plane table surveying is particularly employed for — 3. Large scale maps iv. Plane table survey is useful for — 4. Small scale maps Choose the correct option:
- (i) - 3, (ii) - 4, (iii) - 1, (iv) - 2
- (i) - 4, (ii) - 3, (iii) - 2, (iv) - 1
- (i) - 1, (ii) - 2, (iii) - 4, (iv) - 3
- (i) - 3, (ii) - 2, (iii) - 1, (iv) - 4
Show answer
Answer: (1) (i) - 3, (ii) - 4, (iii) - 1, (iv) - 2
A centring error shows up on paper only at large scales, so accurate centring matters for large-scale maps, while at small scales orientation matters more. Intersection locates points by rays from two stations without measuring distance, so it suits inaccessible points; plane tabling suits open country with good intervisibility. Hence i-3, ii-4, iii-1, iv-2.
The following steps are necessary to obtain sufficient accuracy with the tape: I. Keeping uniform tension on tape for each measurement II. "Breaking" tape on slopes are necessary to keep the tape level III. Keeping accurate count of the stations IV. Keeping the tape on the line being measured The correct sequence of these steps is:
- IV, II, I, III
- II, III, IV, I
- IV, I, II, III
- III, II, I, IV
Show answer
Answer: (1) IV, II, I, III / (3) IV, I, II, III
Taping starts by holding the tape on the line being measured (IV); it is then pulled with uniform tension (I), held level by breaking the tape on slopes (II), and each tape length is tallied so the count of stations is not lost (III), giving IV, I, II, III. JKSSB's final key accepts both A and C, the two sequences that begin with keeping the tape on line.
Theory of probability can be applied to
- Cumulative errors only
- Accidental errors only
- Both accidental and cumulative errors
- None of the above is correct
Show answer
Answer: (2) Accidental errors only
Accidental (random) errors are small, equally likely to be positive or negative and follow the normal law of probability, so probable error and least-squares adjustment apply to them. Cumulative (systematic) errors follow a definite law and are removed by calculated corrections, not by probability.
The principle of "working from whole to part" is used in surveying because
- Plotting and mapping becomes easy
- Survey work can be completed quickly
- Accumulation of errors is prevented
- Lower manpower requirement
Show answer
Answer: (3) Accumulation of errors is prevented
A framework of main control points is first fixed with high precision and the details are then filled in by less precise methods. Errors in the minor work stay localised within the framework instead of accumulating and magnifying, as they would when working from part to whole.
The relation between the radius (R) and degree (D) of a curve is
- R = D/1719
- R = 1719/D
- R/D = 1719
- D/R = 1719
Show answer
Answer: (2) R = 1719/D
Degree of curve D is the angle subtended at the centre by a 30 m arc. So 30 = R × D × π/180, giving R = 5400/(πD) = 1718.9/D ≈ 1719/D (R in metres, D in degrees). A sharper curve (larger D) has a smaller radius.
Match list I with list II and select the correct answer using the codes given below the list List - I — List - II a. Topographical survey — 1. To obtain data for carrying out any of project b. Geodetic survey — 2. To show the boundaries of fields, building, etc. c. Engineering survey — 3. To furnish the data for size and shape of the earth. d. Cadastral survey — 4. To show natural features of the country such as rivers, hills, lakes, roads, bridges etc.
- a-1, b-2, c-3, d-4
- a-2, b-1, c-4, d-3
- a-1, b-3, c-4, d-2
- a-4, b-3, c-1, d-2
Show answer
Answer: (4) a-4, b-3, c-1, d-2
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
After fixing the plane table to the tripod, the main operations that are needed at each plane table station are a. Levelling b. Orientation c. Centering The correct sequence for this operation is
- a, b, c
- a, c, b
- c, a, b
- b, c, a
Show answer
Answer: (2) a, c, b
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
A level was set up at a point A and distance to the staff station B was 100 m. The net combined correction due to curvature and refraction as applied to the staff reading is
- 0.00673 m.
- 0.000673 m.
- - 0.000673 m.
- - 0.00673 m.
Show answer
Answer: (3) - 0.000673 m.
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
If three consecutive ordinates are taken at 2 m intervals from a traverse line and measured as 1.8 m, 2.5 m and 2.0 m, then the area between the traverse line, the first and last ordinates and the boundary, by trapezoidal rule, is
- 17.6 sq m
- 8.8 sq m
- 18.8 sq m
- 7.6 sq m
Show answer
Answer: (2) 8.8 sq m
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.
Number of links in a 30 m metric chain is.
- 150
- 180
- 100
- 200
Show answer
Answer: (1) 150
Explanation: open it in the practice app. It needs the ₹149 All-in-One Pass: one payment for every exam on the site.