JKSSB JE Civil 2025 · Question 10

Question 10 of the JKSSB Junior Engineer (Civil) OMR Exam 2025 (2 November) Question Paper (2 November 2025). Try it first, then open the answer and explanation.

  1. JE Civil 2025 · 2 November · Q10 · Surveying · Surveying

    The following steps are necessary to obtain sufficient accuracy with the tape: I. Keeping uniform tension on tape for each measurement II. "Breaking" tape on slopes are necessary to keep the tape level III. Keeping accurate count of the stations IV. Keeping the tape on the line being measured The correct sequence of these steps is:

    1. IV, II, I, III
    2. II, III, IV, I
    3. IV, I, II, III
    4. III, II, I, IV
    Show answer

    Answer: (1) IV, II, I, III / (3) IV, I, II, III

    Taping starts by holding the tape on the line being measured (IV); it is then pulled with uniform tension (I), held level by breaking the tape on slopes (II), and each tape length is tallied so the count of stations is not lost (III), giving IV, I, II, III. JKSSB's final key accepts both A and C, the two sequences that begin with keeping the tape on line.