From a laboratory proctor compaction test data, the mass of the soil and water content is found to be 1100 g and 10% respectively. The volume of the proctor mould used is 1000 cm³, then the dry density (γd) of the soil is
- 1 g/cm³
- 1.10 g/cm³
- 1.50 g/cm³
- 1.15 g/cm³
Show answer
Answer: (1) 1 g/cm³