  1. JE Civil 2025 · 2 November · Q40 · Building Materials & Construction · Building Construction

    When the depth of trench exceeds 1.5 to 2m, and when excavations is made with side vertical, it becomes necessary to support the side by sheeting and bracing. This operation is known as ______

    1. shafts of trench
    2. electro-osmosis
    3. boning of trench
    4. timbering of trench
    Show answer

    Answer: (4) timbering of trench