WBPSC IDO 2019 Screening Test · Question 9

Question 9 of the WBPSC Industrial Development Officer (IDO) Screening Test 2019 Question Paper (22 December 2019). Try it first, then open the answer and explanation.

  1. IDO 2019 · Screening Test · Q9 · Mental Ability & Arithmetic · Arithmetic

    P and Q can do a work in 12 days, Q and R in 15 days, R and P in 20 days. Find in what time P will do it alone?

    1. 30 days
    2. 20 days
    3. 24 days
    4. 60 days
    Show answer

    Answer: (1) 30 days

    Adding the three pairs: 2(P + Q + R) = 1/12 + 1/15 + 1/20 = 12/60 = 1/5, so P + Q + R = 1/10 per day. P = 1/10 − (Q + R) = 1/10 − 1/15 = 1/30, so P alone takes 30 days.