P and Q can do a work in 12 days, Q and R in 15 days, R and P in 20 days. Find in what time P will do it alone?
- 30 days
- 20 days
- 24 days
- 60 days
Show answer
Answer: (1) 30 days
Adding the three pairs: 2(P + Q + R) = 1/12 + 1/15 + 1/20 = 12/60 = 1/5, so P + Q + R = 1/10 per day. P = 1/10 − (Q + R) = 1/10 − 1/15 = 1/30, so P alone takes 30 days.