UPSC Civil Services (Main) 2024 · GS Paper III
UPSC Mains 2024 GS 3 · Q8: model answer
General Studies Paper III: Technology, Economic Development, Bio-diversity, Environment, Security and Disaster Management · Environment and Biodiversity.
What role do environmental NGOs and activists play in influencing Environmental Impact Assessment (EIA) outcomes for major projects in India? Cite four examples with all important details.
Syllabus: Environment and Biodiversity · Environmental impact assessment and laws
Environmental Impact AssessmentPublic hearingEnvironmental activismJudicial review
Environmental Impact Assessment (EIA) predicts a project's environmental and social effects before it is approved. Made mandatory in 1994 under the Environment (Protection) Act, 1986 and now governed by the EIA Notification, 2006, it has four stages: screening, scoping, public consultation and appraisal. The public hearing, appeals to the National Green Tribunal (2010) and public interest litigation give NGOs and activists their main entry points.
1. Role of NGOs and activists
- Watchdogs on EIA quality: they expose copied or one-season baseline data, hidden forests and wildlife, and under-counted displacement.
- Voice of affected people: they translate technical reports, mobilise villagers for public hearings and record objections.
- Litigation: petitions before the NGT, High Courts and the Supreme Court can suspend clearances or force fresh studies.
- Expert alternatives and advocacy: independent studies by groups such as the Centre for Science and Environment, and campaigns against dilution, such as the opposition to the 2020 draft EIA Notification.
- Monitoring after clearance: they check compliance with clearance conditions and report violations.
2. Four examples
| Project | Who | Concern | Outcome |
|---|---|---|---|
| Silent Valley hydel project, Kerala (1970s–1984) | Kerala Sastra Sahitya Parishad, poet Sugathakumari, scientists such as Salim Ali | Loss of rare evergreen rainforest and the lion-tailed macaque | Project shelved after a review committee under M.G.K. Menon; national park declared in 1984 |
| Sardar Sarovar dam, Narmada (1985–2000) | Narmada Bachao Andolan (Medha Patkar, Baba Amte) | Displacement; weak environmental and resettlement planning | Independent review for the World Bank (1992); Bank withdrew (1993); Supreme Court (2000) allowed the dam with resettlement conditions |
| Niyamgiri bauxite mining, Odisha (2010–2014) | Dongria Kondh villagers with local and international groups | Sacred hills, forests and forest rights | Forest clearance refused (2010); Supreme Court (2013) let gram sabhas decide; all 12 rejected; clearance finally refused (2014) |
| Ex-post-facto clearances (2025–26) | Vanashakti (NGO) | Projects cleared after work had begun | Supreme Court (July 2026): prior environmental clearance is the rule |
- Silent Valley: the dam on the Kunthipuzha would have drowned one of the last tracts of undisturbed tropical evergreen forest in the Western Ghats; one of India's first great environmental campaigns, backed by scientists, showed that ecological value could outweigh a power project.
- Narmada: the dam was built, but the movement made resettlement and environmental safeguards conditions of approval, and the controversy led to the World Bank's Inspection Panel (1993).
- Niyamgiri: bauxite from the hills sacred to the Dongria Kondh was meant for Vedanta's alumina refinery at Lanjigarh; activism, the N.C. Saxena Committee's findings on violations of the Forest Rights Act and the Supreme Court made gram sabha consent decisive.
- Vanashakti: one NGO's petition reshaped EIA law for all projects by ruling out routine post-facto approval.
3. Assessment
- Positive: better scrutiny of projects, protection of tribal rights and biodiversity, and a stronger rule of law in environmental governance.
- Concerns: delays and cost overruns; an Intelligence Bureau report (2014) alleged that some foreign-funded NGOs were stalling development; tighter FCRA rules (2020) now limit foreign funding.
- Limits of influence: most projects still receive clearance, as Kudankulam did despite prolonged protests, and hearings are often a formality.
NGOs and activists act as the conscience of EIA, filling gaps left by weak regulators. Making EIA independent and participatory from the start would turn confrontation into constructive engagement.