UPSC Civil Services (Main) 2022 · GS Paper I

UPSC Mains 2022 GS 1 · Q7: model answer

General Studies Paper I: Indian Heritage and Culture, History and Geography of the World and Society · Human and Economic Geography.

Q710 marks150 words2022 · GS Paper I

Examine the potential of wind energy in India and explain the reasons for their limited spatial spread.

Syllabus: Human and Economic Geography · Natural resources and minerals

Model answer · free

Wind potentialSpatial concentrationGrid integrationOffshore wind

Wind power varies with the cube of wind speed, so it pays only where winds are strong and steady. The National Institute of Wind Energy puts India's onshore potential at 1,163.9 GW at 150 m above ground (695.5 GW at 120 m). Yet installed capacity was only 59.2 GW on 30 September 2026 (MNRE), about 5% of the potential, and half of it lies in two States, although India ranks fourth in the world.

1. Potential

  • Onshore: the best resources lie in eight windy States of the west and south: Gujarat, Rajasthan, Maharashtra, Madhya Pradesh, Karnataka, Telangana, Andhra Pradesh and Tamil Nadu; Andhra Pradesh alone has 123.3 GW at 150 m.
  • Taller turbines: higher hubs and longer blades make moderate-wind sites viable, which is why the estimate rises sharply at 150 m.
  • Offshore: India notified a National Offshore Wind Energy Policy in 2015 and targets 30 GW by 2030; in June 2024 the Cabinet approved ₹7,453 crore of viability gap funding for the first 1 GW off Gujarat and Tamil Nadu.
  • Complement to solar: wind blows strongly in the monsoon and at night, so hybrids smooth supply; the target is 100 GW of wind by 2030.

2. Present spread

  • Concentration: Gujarat (17.0 GW) and Tamil Nadu (12.3 GW) had about half of all capacity in September 2026; most of the rest is in Karnataka, Maharashtra, Rajasthan, Andhra Pradesh and Madhya Pradesh.
  • Large gaps: the Indo-Gangetic plains, eastern India and the North-East have almost none.
Gujarat17Tamil Nadu12.3Rest of India29.8
Installed wind capacity, 30 September 2026 (GW, MNRE)

3. Reasons for the limited spatial spread

  • Physical geography: strong, steady winds occur where the monsoon is funnelled through gaps such as the Palghat gap and the Aralvaimozhi pass (Muppandal, Kanyakumari), along the Gujarat coast and over the Thar; the plains and the east have weak, variable winds.
  • Seasonality: most generation comes in the south-west monsoon months, so turbines run well below capacity for much of the year.
  • Land and ecology: turbines and access roads need large tracts; conflicts arise over common lands and orans (sacred groves) in Rajasthan, and over the habitat of the Great Indian Bustard, where the Supreme Court restricted overhead lines (2021) before revising its approach in M.K. Ranjitsinh (2024).
  • Transmission: windy sites are far from big cities; evacuation lines lag behind projects despite the Green Energy Corridors, and financially weak distribution companies delay payments or curtail wind power.
  • Auction economics: competitive bidding since 2017 rewards the windiest sites, so projects cluster, while old, low-height turbines still occupy many of the best sites.
  • Offshore costs: special vessels, port upgrades and higher tariffs have delayed offshore projects.
ConstraintRemedy
Few high-wind sitesTaller turbines; repowering old sites
Seasonal outputWind-solar hybrids; battery and pumped storage
Land and bustard habitatPlanning around sensitive zones
Transmission gapsGreen Energy Corridors; inter-State lines
Weak DISCOMsPayment security; timely dues
Offshore costsViability gap funding; port upgrades
Constraints and remedies

India's wind potential is large but geographically concentrated. Repowering, hybrids with storage, taller turbines that open up moderate-wind regions, offshore wind and stronger transmission can widen its spread and help reach the 500 GW non-fossil target by 2030.

Every model answer here is free

The ₹149 All-in-One Pass opens the rest of the site for 12 months: UPSC Prelims GS Paper I and CSAT with explanations, practice quizzes and timed tests, UPSC CAPF and EPFO, the previous papers of every APPSC, TSPSC, police and SSC exam, every mock test series and the study books.

₹149 · valid for 12 months from the day you pay, on every exam · pay by UPI, card or net banking

Get it for ₹149