Photo: Konark Sun Temple wheel, Joydeep, CC BY-SA 4.0
UPSC Civil Services (Main) 2020 · GS Paper I
UPSC Mains 2020 GS 1 · Q16: model answer
General Studies Paper I: Indian Heritage and Culture, History and Geography of the World and Society · Human and Economic Geography.
India has immense potential of solar energy though there are regional variations in its development. Elaborate.
Syllabus: Human and Economic Geography · Natural resources and minerals
Solar potentialInsolationRegional variationGrid integration
India lies largely in the tropics and receives about 4–7 kWh of solar energy per square metre per day on roughly 300 sunny days; the National Institute of Solar Energy puts its potential at about 748 GWp. Installed solar capacity reached about 171 GW by 30 September 2026 (MNRE). Development is, however, highly uneven: by September 2026 Rajasthan, Gujarat and Maharashtra together had nearly 60% of it.
1. The potential
- High insolation: strongest in the Thar Desert, Gujarat, the Deccan and the clear, cold skies of Ladakh; weaker in the cloudy, rainy North-East, Kerala and the Himalayan foothills.
- Land: arid wastelands in Rajasthan (Bhadla) and the Rann of Kutch (the Khavda park, planned for 30 GW) can host very large parks.
- Distributed solar: rooftops (PM Surya Ghar: over 50 lakh homes by August 2026), farm solar (about 25 lakh pumps under PM-KUSUM), canal tops and floating solar on reservoirs (Omkareshwar; PM Surya Sarovar Yojana, 2026).
2. Regional variations in development
- North-western leaders: Rajasthan leads with about 45 GW and Gujarat is second with about 36 GW (September 2026), thanks to high insolation, cheap wasteland, early policies (Gujarat's solar policy of 2009 and its Charanka park) and transmission under the Green Energy Corridors.
- Western and southern States: Maharashtra, Tamil Nadu, Karnataka (Pavagada) and Andhra Pradesh (Kurnool, Ananthapuram) combine good sunshine with industrial demand and supportive policies.
- Laggards: Uttar Pradesh had under 6 GW in mid-2026 despite its size, and Bihar, West Bengal, Kerala and the North-East far less, because of dense population and costly land, haze or heavy cloud, weak finances of distribution companies and difficult terrain.
- Ladakh: very high potential but remote; a transmission project to evacuate 13 GW of renewable power from Ladakh was approved in 2023.
3. Challenges behind the variation
- Intermittency: solar works only by day; non-fossil sources gave only about 29% of electricity in 2025-26, and evening peaks still need coal or storage.
- Transmission and land: power from desert parks must travel far, and land acquisition and grazing rights cause conflicts.
- Wildlife: power lines in Rajasthan and Gujarat cross the habitat of the critically endangered Great Indian Bustard; in 2024 the Supreme Court balanced its protection with climate goals and recognised a right against the adverse effects of climate change.
- Supply chain: dependence on imported polysilicon and wafers, and a coming wave of panel waste.
| Region | Potential | Status | Main constraint |
|---|---|---|---|
| North-west (Rajasthan, Gujarat) | Highest insolation; wasteland | Leaders: Bhadla, Khavda | Transmission; bustard habitat |
| West and south (Maharashtra, Tamil Nadu, Karnataka, Andhra Pradesh) | High | Large parks and rooftops | Land; DISCOM finances |
| Ladakh | Very high; clear skies | Mostly untapped | Remoteness; long transmission |
| Ganga plain (Uttar Pradesh, Bihar, West Bengal) | Moderate; haze | Lagging | Dense population; costly land |
| North-East and Kerala | Lower; cloud and rain | Small | Terrain; scattered demand |
4. Way forward
- Storage and grids: battery and pumped storage, inter-regional transmission and better forecasting.
- Spreading the gains: rooftop, agri-voltaic and floating solar for land-scarce eastern and northern States, with healthier DISCOMs.
- Self-reliance: domestic manufacturing of cells and wafers, and panel recycling.
India's solar potential is vast and its progress rapid, but the regional imbalance reflects differences in sunshine, land, grids and policy. Distributed solar and storage can make the transition truly national on the way to 500 GW of non-fossil capacity by 2030.