A non-pipeline system takes 50ns to process a task. The same task can be processed in six-segment pipeline with a clock cycle of 10ns. What is the speed-up ratio of the pipeline for 100 tasks?
- 4.76ns
- 40ns
- 40.76ns
- 1ns
Show answer
Answer: (1) 4.76ns