The area between the two isohyets 45cm and 55cm is 100km² and that between 55cm and 65cm is 150km². What is the average depth of annual precipitation over the basin of 250km²
- 50cm
- 52cm
- 56cm
- 60cm
Show answer
Answer: (3) 56cm
By the isohyetal method each strip takes the mean of its bounding isohyets (50 cm and 60 cm), so P = (100 × 50 + 150 × 60)/250 = 14000/250 = 56 cm.