RRB NTPC Graduate CBT 1 2026 (27 March Shift 1) · Question 35
Question 35 of the RRB NTPC Graduate CBT-1, 27 March 2026, Shift 1 (27 March 2026). Try it first, then open the answer. The explanation is in the practice app with the All-in-One Pass.
P and Q can complete a piece of work in 14 days and 19 days, respectively. They work on alternate days, beginning with P. The whole work will be completed in:
- 14 1/19 days
- 16 2/19 days
- 18 3/19 days
- 12 4/19 days
P और Q एक कार्य को क्रमशः 14 और 19 दिनों में पूरा कर सकते हैं। वे P से शुरू करके एकांतर दिनों में कार्य करते हैं। सम्पूर्ण कार्य कितने दिनों में पूरा होगा?
- 14 1/19 दिन
- 16 2/19 दिन
- 18 3/19 दिन
- 12 4/19 दिन
Show answer
Answer: (2) 16 2/19 days
उत्तर: (2) 16 2/19 दिन