    A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    1. 85
    2. 90
    3. 81
    4. 80
    Show answer

    Answer: (3) 81