APPSC FRO Mains 2020 General Forestry 2 · Question 76
Question 76 of the APPSC Forest Range Officer Mains 2020: Paper IV General Forestry II (19 March 2020). Try it first, then open the answer. The explanation is in the practice app with the All-in-One Pass.
The precedence diagramming method is also called:
- the marginal analysis method
- the activity-on-node method
- the cost transfer method
- the differential cost method
Show answer
Answer: (2) the activity-on-node method