How does the concept of risk management integrate with risk-benefit analysis?
- Risk management eliminates the need for risk-benefit analysis.
- Risk-benefit analysis is used to inform risk management decisions.
- Risk-benefit analysis occurs only after risk management is implemented.
- Risk management focuses solely on minimising costs.
Show answer
Answer: (2) Risk-benefit analysis is used to inform risk management decisions.